48 models in our EOSL library have a 2025 end of service life date. All of them have passed it. On that date the OEM stops selling support contracts for a model. The table below lists each one by date, with the source for the date.
What EOSL means for a box in production
End of service life is the date the manufacturer stops selling support contracts for a model. The hardware keeps running. What goes away is the OEM parts depot and the OEM engineers for that model. After that date, a failed drive or controller is your problem unless someone else holds the spares.
What you can do now
- Refresh
- You replace hardware that still runs, on a date the OEM picked.
- Self-spare
- You buy used parts from brokers and fix it in-house. It works until the part you need is the one no broker has.
- Third-party maintenance
- We support these models 3 to 5+ years past EOSL with a 4-hour on-site SLA. Price maintenance or find parts.
EOSL dates by month
October has the most, with 13. February, March, June and November have none.
All 48 models, by EOSL date
Showing 48 of 48 models.
- NetApp DS2246Past EOSL
Jan 31, 2025 · EOSL databases · Parts
- NetApp DS4246Past EOSL
Jan 31, 2025 · EOSL databases · Parts
- Cisco ASR 1004Past EOSL
Apr 30, 2025 · OEM notice · Parts
- Cisco Nexus 3132Q-XPast EOSL
Apr 30, 2025 · OEM notice · Parts
- Cisco Meraki MX400 / MX600Past EOSL
May 20, 2025 · OEM notice · Parts
- HPE ProLiant BL460c Gen9Past EOSL
Jul 22, 2025 · EOSL databases · Parts
- HPE ProLiant DL360 Gen9Past EOSL
Jul 22, 2025 · EOSL databases · Parts
- HPE ProLiant DL380 Gen9Past EOSL
Jul 22, 2025 · EOSL databases · Parts
- HPE ProLiant DL560 Gen9Past EOSL
Jul 22, 2025 · EOSL databases · Parts
- HPE ProLiant DL580 Gen9Past EOSL
Jul 22, 2025 · EOSL databases · Parts
- IBM Power S812 (8284-21A)Past EOSL
Jul 31, 2025 · OEM notice · Parts
- Cisco Nexus 3048Past EOSL
Aug 31, 2025 · OEM notice · Parts
- Dell Compellent SCv2000Past EOSL
Aug 31, 2025 · EOSL databases · Parts
- Dell Compellent SCv2020Past EOSL
Aug 31, 2025 · EOSL databases · Parts
- Dell Compellent SCv2080Past EOSL
Aug 31, 2025 · EOSL databases · Parts
- Dell Data Domain DD6800Past EOSL
Aug 31, 2025 · EOSL databases · Parts
- Dell Data Domain DD9300Past EOSL
Aug 31, 2025 · EOSL databases · Parts
- Dell Data Domain DD9800Past EOSL
Aug 31, 2025 · EOSL databases · Parts
- Cisco ASA 5525-XPast EOSL
Sep 30, 2025 · OEM notice · Parts
- Cisco ASA 5545-XPast EOSL
Sep 30, 2025 · OEM notice · Parts
- Cisco ASA 5555-XPast EOSL
Sep 30, 2025 · OEM notice · Parts
- Cisco Nexus 2232PPPast EOSL
Sep 30, 2025 · OEM notice · Parts
- Cisco Nexus 2232TM-EPast EOSL
Sep 30, 2025 · OEM notice · Parts
- Cisco Nexus 2332TQPast EOSL
Sep 30, 2025 · OEM notice · Parts
- Cisco Nexus 2348TQPast EOSL
Sep 30, 2025 · OEM notice · Parts
- Cisco Nexus 56128PPast EOSL
Sep 30, 2025 · OEM notice · Parts
- Cisco Nexus 5624QPast EOSL
Sep 30, 2025 · OEM notice · Parts
- Cisco Nexus 5648QPast EOSL
Sep 30, 2025 · OEM notice · Parts
- Dell PowerSwitch N2024Past EOSL
Oct 29, 2025 · EOSL databases · Parts
- Dell PowerSwitch N2024PPast EOSL
Oct 29, 2025 · EOSL databases · Parts
- Dell PowerSwitch N2048Past EOSL
Oct 29, 2025 · EOSL databases · Parts
- Cisco Catalyst 3850Past EOSL
Oct 31, 2025 · OEM notice · Parts
- Cisco Catalyst 4500-XPast EOSL
Oct 31, 2025 · OEM notice · Parts
- Cisco Catalyst 4500E (4503-E/4506-E/4507R+E/4510R+E)Past EOSL
Oct 31, 2025 · OEM notice · Parts
- Cisco Catalyst 6500 Supervisor 2T (VS-S2T-10G/XL)Past EOSL
Oct 31, 2025 · OEM notice · Parts
- Cisco Catalyst 6506-EPast EOSL
Oct 31, 2025 · OEM notice · Parts
- Cisco Catalyst 6509-EPast EOSL
Oct 31, 2025 · OEM notice · Parts
- Cisco Catalyst 6509-V-EPast EOSL
Oct 31, 2025 · OEM notice · Parts
- Cisco Catalyst 6513-EPast EOSL
Oct 31, 2025 · OEM notice · Parts
- Cisco Catalyst 6840-XPast EOSL
Oct 31, 2025 · OEM notice · Parts
- Cisco Catalyst 6880-XPast EOSL
Oct 31, 2025 · OEM notice · Parts
- IBM FlashSystem 9100 (9846-AF7)Past EOSL
Dec 31, 2025 · OEM notice · Parts
- IBM FlashSystem 9150 (9848-AF8)Past EOSL
Dec 31, 2025 · OEM notice · Parts
- IBM Storwize V5010E (2072-224)Past EOSL
Dec 31, 2025 · OEM notice · Parts
- IBM Storwize V5030E (2072-324)Past EOSL
Dec 31, 2025 · OEM notice · Parts
- IBM Storwize V5100 (2078-424)Past EOSL
Dec 31, 2025 · OEM notice · Parts
- IBM Storwize V7000 Gen2/Gen2+ expansion (2076-24F)Past EOSL
Dec 31, 2025 · OEM notice · Parts
- IBM Storwize V7000 Gen3 NVMe (2076-724)Past EOSL
Dec 31, 2025 · OEM notice · Parts
Where the dates come from
32 of these 48 dates come from the OEM's own lifecycle notice. 16 come from two or more independent EOSL databases that agree. Dates can change, so confirm them for your serial numbers. Each model page has a free email alert 12 months before its EOSL date and again on the date.
Short answers
Which data center hardware reached end of service life in 2025?
48 models in the Datacenterservices.ai EOSL library have a 2025 end of service life date: Cisco 24, Dell 9, IBM 8, HPE 5, NetApp 2. All of those dates have passed. The last was Dec 31, 2025.
What happens when data center hardware reaches EOSL?
The OEM stops selling support contracts for the model. The hardware keeps running, but OEM parts and engineers are no longer available for it. Third-party maintenance providers such as Datacenterservices.ai support these models for 3 to 5+ years past the EOSL date, with a 4-hour on-site SLA.
Where do these EOSL dates come from?
32 of the 48 dates come from the OEM's own lifecycle notice. 16 come from two or more independent EOSL databases that agree. Each row in the table shows its source, linked where one is on file. Dates can change, so confirm them for your serial numbers.